Rabigh Desalination Plant
- PROJECT
- Rabigh Desalination Plant
- CLIENT
- SETE Technical Service SA (Developper of an Aramco's B.O.Y. Project)
- SCOPE OF WORK
- Electrical and instrumentation supplier for Rabigh Desalination Plant
- CONTRACT
- Direct
- AMOUNT
- 1.500.000,00 €
- PERIOD OF EXECUTION
- Coming into force: July 2003
Completion date: October 2005
- GAVAZZI SCOPE
- Engineering: Electrical, instrumentation and process engineering (Basic and detail)
Procurement:
Main equipment
- P.L.C. (Programmable Logic Controller)
- Field Instrumentation
- Transformers
- Medium voltage switchgear
- Low voltage switchgear
Bulk material
- Power and instrumentation cables
- Cable way
- Lighting system
- Grounding and lightning system
Auxiliary system
- UPS system
- Communication system
- Fire fighting system
Construction:
Erection supervision
Tests and commissioning
Start-up