CIRA - 132Kv Substation (Italy)
- PROJECT
- CIRA - 132Kv Substation (Italy)
- CLIENT
- CIRA - Centro Italiano di Ricerca Aerospaziale - Capua
- SCOPE OF WORK
- New 132kV substation for the electrical distribution to the Aerospace Research Centre of Capua
- CONTRACT
- Direct
- AMOUNT
- Euro 4.260.110,00
- PERIOD OF EXECUTION
- Coming into force: June 1997
Completion date: December 1998
- GAVAZZI SCOPE
- Engineering: Detailed engineering of the civil and electromechanical works
Procurement:
Main equipment
- No. 1 transformer 150/32,5 kV 90 MVA
- No. 2 transformers 150/20 kV 25 MVA
- No. 1 transformer 150/20 kV 12,5 MVA
- 132 kV Equipment
- MV Condensators
- 20 and 32 kV panels
- Auxiliary transformers and panels
- Supervisory system (SCADA)
Auxiliary system
- D.C. systems
- HV/MV Protections
Construction:
Civil works
Electromechanical works
Tests, commissioning and start-up