Italiana Coke - Cogeneration Power Plant
- PROJECT
- Italiana Coke - Cogeneration Power Plant
- CLIENT
- Italiana Coke - Cairo Montenotte
- SCOPE OF WORK
- New cogeneration power plant operating with coke gas, constituted of No. 8 endothermic engines of 2,4 MVA and of a steam turbine of 1 MW
- CONTRACT
- Acquired by the Temporary Consortium Association constituted by:
- INTERGEN / DEUTZ (Leader)
- CARLO GAVAZZI IMPIANTI SpA
- AMOUNT
- Total of the contract Euro 16.526.620,00
CARLO GAVAZZI share Euro 6.197.482,00
- PERIOD OF EXECUTION
- Coming into force: June 1996
Completion date: February 1999
- GAVAZZI SCOPE
- Engineering: Basic and detailed engineering of the thermal cycle, of the electromechanical and instrumental plants and drive
Procurement:
Main equipment
- Thermal cycle including boiler
- Turbine of 1 MW
- Substation 20/132kV
- Elevator transformer 25 MVA
- Unit transformers BT/MT
- MV 20kV panels
- LV Power Center and MCC panels
- Automation and supervision plant with DCS
Bulk material
- MV and LV, power, command and control cables
- Grounding and lightning protection
Auxiliary system
- Protection system
- Lighting plants, FM sockets and low current systems
Construction:
Erection works
Commissioning and start-up
Training