Power Station of Pont Ventoux - Susa (Italy)
- PROJECT
- Power Station of Pont Ventoux - Susa (Italy)
- CLIENT
- A E M Torino
- SCOPE OF WORK
- HVAC, Electrical and Control systems for the new hydroelectric power plant 2 x 85 MVA
- CONTRACT
- Awarded to a Temporary Consortium Association of companies constituted by: CARLO GAVAZZI IMPIANTI SpA (Leader), NUOVA MAGRINI GALILEO SpA
- AMOUNT
- Total of the contract Euro 14.226.000,00
CARLO GAVAZZI share Euro 12.680.000,00
- PERIOD OF EXECUTION
- Coming into force: August 2000
Final acceptance: 2008
- GAVAZZI SCOPE
- Engineering: Basic and detailed engineering
Engineering Tot. Hours
60.000
Procurement:
Main equipment
- GIS substation 132 kV
- No. 11 auxiliary transformers, various sizes
- MV/LV Bus-bars
- MV 15 kV and 6 kV switchgears
- LV Power Center and MCC switchboards
- High and medium voltage protection system
- Emergency generator units, 200 kVA (n. 2), 500 kVA (n. 1), 2000 kVA (n. 1)
- D.C. system and U.P.S.
- Distributed Control System and supervisory package
Value of the Supplies
8.000.000
Bulk material
- Cables 132 kV (No. 3 tern)
- MV, LV, power, command and control cables
Auxiliary system
- HVAC
- Lighting system and small power receptacles
- Telephone, interphone, TVCC plant, fire detection and fighting system, LAN for offices
- Grounding and lightning protection
Construction:
Electrical and instrumentation works
Tests, commissioning and start-up
Provisional operation (one year)
Construction Tot. Hours
110.000