Power Station of Servola (TS)

PROJECT
Power Station of Servola (TS)
CLIENT
Elettra GLT SpA
SCOPE OF WORK
New cogeneration power plant combined cycle 145 plus 95 MVA realized at siderurgical factory of SERVOLA (TS)
CONTRACT
Acquired by the Temporary Consortium Association constituted by:
  • ANSALDO ENERGIA SpA (Leader)
  • CARLO GAVAZZI IMPIANTI SpA
  • CARLO GAVAZZI COSTRUZIONI SpA
  • MORAS COSTRUZIONI SpA
AMOUNT
Total of the contract Euro 120.318.965,00
CARLO GAVAZZI share Euro 18.075.000,00
PERIOD OF EXECUTION
Coming into force: August 1998
Completion date: December 2000
GAVAZZI SCOPE
Engineering: Process and basic engineering

Procurement:
Main equipment
  • 150kV outdoor substation
  • 1 step-up transformer 30MVA 11/150kV
  • Auxiliary transformer
  • MV and LV auxiliary switchgears
  • Emergency diesel generators
  • 2x10MW boilers for biomass fuel
  • 2x10MW steam turbines and thermal cycle equipment
  • 2 flue gas treatment filterse
  • 2 air condenser
  • DCS system
  • All field instruments and local control panels
Bulk material
  • Cables 132 kV (No. 3 tern)
  • MV, LV, power, command and control cables
Auxiliary system
  • Lighting plant and FM sockets
  • Telephone, interphone, TVCC plant, watches, LAN for offices
  • Cathodic protection plant
  • Grounding and lightning protection
Construction:
Electrical and instrumentation works
Tests, commissioning and start-up