400/220/110/ KV Substation of Tirana (Tirana 2) - Albania

PROJECT
400/220/110/ KV Substation of Tirana (Tirana 2) - Albania
CLIENT
APMU / MECE
FINAL CLIENT
OST
SCOPE OF WORK
Engineering, procurement, civil works and installation/commissioning of the 400/220/110 kV substation
CONTRACT
Acquired by the Temporary Consortium Association constituted by:
  • ANSALDO T&D (Leader)
  • CARLO GAVAZZI IMPIANTI SpA.
AMOUNT
Total Contract value Euro 24.629.000,00
Value of CGI’s share Euro 10.000.000,00
PERIOD OF EXECUTION
Coming into force: October 27, 2008
Completion date (scheduled): 2010
GAVAZZI SCOPE
Engineering: Basic and detailed engineering
Engineering Tot. Hours
15.000

Procurement:
Main equipment
  • No. 2 Autotransformer 300 MVA
  • No. 2 Autotransformer 120 MVA
  • No. 7 Circuit breakers 110 KV
  • No. 22 Disconnecting switches 110 KV
  • No. 20 Capacitive voltage Transformers
  • No. 21 Current Transformers 110 Kv
  • No. 18 Surge arresters 110 Kv
  • No. 11 Circuit breakers 220 KV
  • No. 34 Disconnecting switches 220 KV
  • No. 26 Capacitive voltage Transformers
  • No. 33 Current Transformers 220 Kv
  • No. 30 Surge arresters 220 Kv
  • No. 4 Line traps 220 Kv
  • No. 5 Circuit breakers 400 KV
  • No. 48 Disconnecting switches 400 KV
  • No. 12 Capacitive voltage Transformers
  • No. 15 Current Transformers 400 Kv
  • No. 12 Surge arresters 400 Kv
  • MV 20kV switchgear
  • LV power center
  • High voltage protection and control system
  • Emergency generator
  • DC system and UPS
  • Auxiliary transformers
Value of the Supplies
20.325.000

Bulk material
  • HV conductor, insulators and HV connectors
  • Steel structures
  • Power and control cables
Auxiliary system
  • HVAC
  • Lighting system and small power receptacles
  • Grounding and lightning protection
Construction:
Civil works and electromechanical erection; Tests, commissioning and start-up Provisional operation

Construction Tot. Hours
120.000