2x350 MW GAS/OIL Fired Units Thermal Power Plant El Tebbin (Egypt)
- PROJECT
- 2x350 MW GAS/OIL Fired Units Thermal Power Plant El Tebbin (Egypt)
- CLIENT
- Ansaldo Caldaie
- FINAL CLIENT
- CEPC (Cairo Electricity Production Company)
- SCOPE OF WORK
- Engineering, procurement and construction of the electrical, instrumentation, automation and control works for 2x350 MW gas/oil fired unit boilers
- CONTRACT
- Nominated subcontractor
- AMOUNT
- Contract value Euro 7.240.000,00
- PERIOD OF EXECUTION
- Coming into force: May 2007
Completion date (scheduled): March 2010
- GAVAZZI SCOPE
- Engineering: Basic and detailed engineering
Engineering Tot. Hours
8.000
Procurement:
Main equipment
- BMS / BPS system
- CEMS
- Vibration monitoring system
- Fire fighting and detection system
- Boiler and Field instrumentation
- PLC sootblower system
- MCC switchboards and distribution panels
Value of the Supplies
6.000.000
Bulk material
Auxiliary system
- MCC enclosure with HVAC
- Lighting system and small power receptacles
- Secondary grounding and lightning protection
Supervision:
Construction supervision assistance from CGImpianti
Supervision Tot. Hours
4.000
Construction:
Ansaldo Caldaie Egypt awarded the construction contract directly to Carlo Gavazzi Egypt for a total amount of 2.419.000,00