Extension of Electric Power Plant 3x20 MVA - Alrar (Algeria)
- PROJECT
- Extension of Electric Power Plant 3x20 MVA - Alrar (Algeria)
- CLIENT
- Sonatrach ENC
- SCOPE OF WORK
- Electrical, Instrumentation & Control, Telecom, Fire Fighting packages EPC
- CONTRACT
- Awarded to the open consortium formed by Bonatti SpA (Leader), Carlo Gavazzi Impianti SpA
- AMOUNT
- Euro 15.700.000,00
- PERIOD OF EXECUTION
- Coming into force: March 2009
Completion date (scheduled): May 2011
- GAVAZZI SCOPE
- Engineering: Basic and detailed engineering
Engineering Tot. hours 23.000
Procurement:
Main equipment
- SCADA/Electrical control system
- DCS/ESD system
- Telecom (CCTV, PABX, Antintrusion, Interphone, LAN, Radio)
- Fire & Gas detection and Fire protection
- Step-up Transformer
- MV and LV transformers
- MV e LV switchgear
- PC e MCC cabinet
- DC & UPS system
- New 66 kV substation and protections
- Relocation of existing 66 KV OTL
Bulk material
- HV cables
- MV and LV Power cables
- I&C cables
- Valves and field instruments
Construction:
Installation of electrical and I&C systems
Pre-commissioning
Commissioning
Start-up
Training