New Buildings and Infrastructure for the Carabineer Authorities in Florences
- PROJECT
- New Buildings and Infrastructure for the Carabineer Authorities in Florences
- CLIENT
- Ministry of Infrastructure
- SCOPE OF WORK
- Engineering, procurement and construction of the whole technological systems including HVAC, electrical and low current (special) systems
- CONTRACT
- Awarded to a Temporary Association of companies formed by Astaldi (leader), Rosso, Siri, Carlo Gavazzi Impianti (Members) A Joint Venture to execute the contract has been set-up
- AMOUNT
- Contract value Euro 261.000.000
Value of CGI’s share Euro 41.700.000
- PERIOD OF EXECUTION
- Coming into force: 2006
Completion date (scheduled): 2010
- GAVAZZI SCOPE
- Engineering: Mechanical, Electrical and low current systems engineering
Engineering Tot. Hours
CGI scope:
20.000
Procurement:
Main equipment
- Chillers
- Boilers
- Air treatment units
- Pumps
- MV/LV transforming station
- Power centers and distribution panels
- Motor – generator set
- UPS groups
- LV main and secondary distribution
- Lighting and small power system
Values of the Supplies:
CGI scope and/or under CGI supervision
20.000.000
Auxiliary system
- Access control and security system
- Interphone, TVCC system
- Electrical supervisory system
- Fire detection system
- Fire fighting system
- Plumbing system
Construction:
Erection of mechanical, Electrical and auxiliary systems; Gas and water network; Fire fighting; Tests and start-up
Construction Tot. Hours
CGI scope and/or under CGI supervision:
500.000