GAS Storage Station - Cortemaggiore (Italy)
- PROJECT
- GAS Storage Station - Cortemaggiore (Italy)
- CLIENT
- ENI SpA - AGIP Division
- SCOPE OF WORK
- Revamping of Gas Storage station and related Clusters
- CONTRACT
- EPC contract acquired by the Temporary Consortium Association constituted by:
- ABB INDUSTRIA SpA (Leader)
- CARLO GAVAZZI IMPIANTI SpA
- AMOUNT
- Total Contract Amount Euro 1.910.890,00
CARLO GAVAZZI share Euro 723.040,00.
- PERIOD OF EXECUTION
- Coming into force: November 1999
Completion date: September 2000
- GAVAZZI SCOPE
- Engineering: Instrumentation and mechanical detailed engineering
Procurement:
Main equipment
- Distributed control system for station and 5 clusters
- Barriers/ Interposing relays cabinets
- Field instrumentation
- Control and On-Off Valves
- Hand valves and fittings up to 2”
- Electropneumatic local panels
- Fiber optic network between main station and clusters
Bulk material
- Instrumentation and mechanical bulk materials
Construction:
Plant Shut-Down schedule Hot & Cold Works, including:
- Disconnection, Removal or Relocation of existing equipment
- Installation and Connection of new equipment/instrumentation in Control Room
- Field instrumentation and connection to Control Room
- Hot taps & Tie-in interconnections between the new and the existing piping
Field tests, precommissioning and commissioning